Completed 2024
Dec 2024 - Ribbon cutting Ceremony
OCT 2024 - Light Rail Proximity
Sept 2024 - amenities in progress
July 2024 - Banners Up
May 2024 - Punch Walk Begins
APR 2024 - Lighting and Punch walk Prep
Mar 2024 - SIding in Progress
Jan 2024 - Crane Dismantle
Q4 2023 - WaterProofing
132 NE 145th Street, Shoreline, Washington
Just steps away from Sound Transit’s future 145th street lightrail station (opening 2024), The Line features 241 residences and 1,900+ sqft of retail. Designed by Tiscareno Architects, this 7-story apartment community is currently under construction and will open to residents in late 2024.




Q3 2023 - FRAMING
JULY 2023 - 3RD FLOOR FRAMING


June 2023 - Framing Begins
May 2023 - SECOND FLOOR

April 2023 - First Floor